Illustrative image – not actual.Indian Oil Corporation (IOC) has plans to set up a naphtha
cracker complex at an estimated cost of Rs.6,000 crore. The project cost is inclusive
of a Rs.600 crore foreign exchange component.
Though the location for the cracker complex has not
yet been finalised, it would be either in southern or western region of India. The
project is expected to be completed in 48 months from the date of final
investment approval. The company has already obtained a letter of intent for
this project.
According to reports, Tamil Nadu Industrial
Development Corporation had indicated participation in this project.
IOC is also considering setting up a Rs.2,000 crore (inclusive
of a Rs.200 crore foreign exchange component) para-xylene (PX) / purified terephthalic
acid (PTA) complex at either its Gujarat or Haldia Refinery in West Bengal. The
project is expected to be completed in 42 months from the date of final
investment approval and would generate 2,50,000 tonnes per year of PX
(intermediate) and/or 3,50,000 tonnes per annum of PTA.
After the expansion of IOC’s Koyali Refinery in
Gujarat, to 13.5 million tonnes, adequate naphtha would be made available for the
para-xylene plant in the complex. The complex would have facilities for utilising
para-xylene for production of PTA, catalytic reformer unit, separation of
xylenes, parex unit, isomerisation unit and toluene/C9 aromatic
disproportionation/ trans-alkylation unit for para-xylene production and
downstream process units for production of PTA besides grassroot
infrastructure.
Besides these projects, IOC is also planning to set up a PTA complex at Panipat in Haryana, which is likely to be commissioned in August 2004.