Illustrative image – not actual.Indian Oil Corporation (IOC) has plans to install a Rs.1,179 crore crude handling facility on western coast of India. This project would include construction of adequate tankages on the west coast, dock lines from jetty to the shore tank farm at the selected port and laying associated crude oil pipeline system from west coast to Viramgram (Gujarat), to handle and transport additional 17 million tonnes of crude oil.
An amount of Rs.100 crore has been allocated for 2002-03
towards this project and presently, a suitable port for this facility is being
studied.
The facility is expected to be completed within 28
months from the date of approval. With this facility in place, IOC would be
able to meet the increased crude oil requirements of the refineries at Koyali
(Gujarat), Mathura (Uttar Pradesh) and Panipat (Haryana) after expansion.
Meanwhile, the IOC board has already approved the
proposal to augment Salaya-Mathura pipeline system (Viramgram-Chaksu section to
26 million tonnes, Chaksu-Panipat section to 15 million tonnes and the
Chaksu-Mathura section to 9.5 million tonnes). This pipeline expansion is
estimated to cost Rs.1,734 crore.
The company board has also approved the laying of a
pipeline from Viramgram to Koyali (Gujarat) at a cost of Rs.329 crore.
IOC’s proposed crude handling facility and the
associated pipelines would be used for onward transportation of crude to
Viramgram through the above mentioned approved pipeline projects.