India Oil Corporation has planned to lay a petroleum products pipeline between Chennai and Bangalore. Work on the same is expected to start after the initial survey.

The IOC board has already accorded "first stage clearance" for the 290-km pipeline, which is expected to cost about Rs.250 crore. This will be followed by a detailed feasibility report before the project is taken up.

Meanwhile, IOC will also be approaching the Railways for a freight discount. If the Railways offer a discount of more than 25 per cent over the existing rates, the pipeline might not be feasible.

In another development, IOC expects to commission its Chennai-Tiruchi-Madurai (CTM) product pipeline by the end-July 2005. The first consignment is expected to be delivered to Madurai on 15 August 2005. Once the CTM pipeline is fully commissioned, it will supplant 25 tanker-moves (each of 12,000 litres) per hour hour.

IOC had built tankages at Sankari, in Salem district, Madurai and Tiruchi as part of this pipeline project. In the first stage, this pipeline will have a capacity of 1.8 million tpa and when fully commissioned in 2010 with a pumping station at Asanur, the capacity will go up to 2.3 million tpa.

IOC has also planned a new pipeline between Manali and the Meenambakkam airport. This 90 km pipeline, costing around Rs.50 crore, will transport aviation turbine fuel from Manali (the site of Chennai Petroleum's refinery) to Meenabakkam via Sriperumbudur.