Illustrative image – not actual.Work
on Indian Oil Corporation’s Paradip Refinery in Orissa, which has almost come
to a standstill, has begun to cause concern to Paradip Port Trust (PPT). As per
the project plan, PPT was supposed to construct a jetty for import of crude oil
required for IOC’s proposed refinery.
Even as PPT is almost ready with its
jetty, having spent over Rs.50 crore in the project, work on the refinery is
progressing at a much slower pace. Only limited work on the refinery project – covering
areas of land reclamation, single buoy mooring and constructing of the pipeline
between the jetty and the refinery site – is currently underway. For the rest,
project work has come to a virtual halt.
The project was put on hold by IOC
following the Orissa Government’s decision of withdrawing sales tax concession
to the products to be manufactured from the refinery. The proposed refinery
would have a capacity of 9 million tpa, expandable to 12 million tpa at a later
stage.
PPT now fears that if the refinery
project gets indefinitely delayed, it would result in gross under-utilisation
of the jetty.