Illustrative image – not actual.The
Board of Indian Oil Corporation (IOC) would be considering the proposal of
expanding the capacity of the Panipat Refinery, in July 2001. The company’s Investment
Review Committee has already approved the project in June 2001. The project
envisages the doubling of the refinery’s capacity to 12 million tpa by
installing a new 6 million tpa crude distillation unit. The project also
entails the setting up of a hydrocracker unit and a coking unit. The project
has an estimated gestation period of 30 months.
The Panipat Refinery is IOC’s newest
refinery (the seventh) and was commissioned in May 1998. IOC has a total
refining capacity of 35.6 million tpa and accounts for 31.4 per cent of India’s
total refining capacity of around 113 million tpa.