Illustrative image – not actual.The Indian Oil Corporation (IOC) is awaiting a decision from the state government for completion of the Rs 490 crore storage terminal at Puthuvype.
IOC has completed works on the Rs 225 crore multi-user liquid terminal (MULT) jetty for unloading LPG at Cochin Port.
However, long drawn protests and indecision on part of the state government has pushed the LPG import terminal project worth Rs 715 crore into uncertainty.
The LPG Import Terminal has got two major facilities like the multi-user liquid terminal (MULT) jetty for unloading LPG at Cochin Port and the storage terminal at Puthuvype which is in limbo due to protests.
LPG from ship tankers will be unloaded at MULT and transferred to the storage terminal through 3.5 km long underground pipeline. The project was scheduled to be completed in February 2018, but only 40 percent of the work for the storage terminal has been completed.
Apart from LPG, other petroleum products, including crude oil, diesel and petrol, can be loaded and unloaded at MULT.
The capacity of MULT is 4.52 million tpa, including LPG. The draft available at MULT is 13.5 mtr which will facilitate very large gas carriers and very large crude carriers to berth there.