Illustrative image – not actual.
The integrated rural piped water supply (IRPWS) Phase-I project for 11 water-stressed villages in Rengali and Dhankauda blocks of the district will be operational by December 2017.
The civil, mechanical and electrical work, excluding the distribution system, has already been completed. Presently, a trial run is being conducted for the project.
The estimated cost of the project is Rs 12.42 crore.
Under the project, a water treatment plant with a capacity of five MLD, besides an overhead tank with capacity of two lakh ltr, has been constructed along SH-10 at Pradhanpali under Dhankauda block.
An overground tank with a capacity of 6.50 lakh ltr has also been constructed at Kilasama Hillock along the highway.
The foundation stone for the project was laid on 27 February 2015.
Water for the project is being drawn from Hirakud Dam reservoir. The overhead tank at Pradhanpali will supply water to Pitapali, Gaudapali, Bad Pradhanpali, Gunchhamal, Pradhanpali, Jharghati and Kumbharakata villages in Dhankauda block.
Similarly, the overground tank at Kilasama Hillock will supply water to Kilasama in Dhankauda block besides Rengali, Ganesh Nagar and Ramchandra Nagar, in Rengali block.