Initial trial for Chennai Metro Rail’s Phase-I to begin by February 2020Illustrative image – not actual.

Chennai Metro Rail (CMRL) will carry out an initial trial in Phase-I extension project from Washermanpet to Wimco Nagar in Tamil Nadu that covers nearly nine km by the end of February 2020.

CMRL is likely to run a shunting loco in the underground stretch from Washermanpet to Korukkupet initially, and do an inspection of how it works.

Currently, tracks are being laid in this nine km stretch; in the underground section, the track has already been laid but work is still on for the elevated section which will be done by February 2020. If it gets completed, trial run will be done for the whole stretch.

Subsequently, after trials with the shunting loco, CMRL will run a trial with trains. This is likely to happen by April 2020.

As CMRL has been planning to open this stretch by June 2020, the beginning of such trials is crucial and only after they are proved safe and all the hitches are corrected, can the section become operational for public.