As many as 470 infrastructure projects, each worth Rs 150 crore or above, have been hit by cost overruns totalling more than Rs 4.38 lakh crore.
The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs 150 crore and above. Of the 1,737 such projects, 470 reported cost overruns and 525 were delayed.
The total original cost of implementation of 1,737 projects was Rs 22,33,409.53 crore and their anticipated completion cost is likely to be Rs 26,71,440.77 crore, which reflects overall cost overruns of Rs 4,38,031.24 crore (19.61 percent of original cost).
The expenditure incurred on these projects till April 2021 is Rs 13,16,032.62crore, which is 49.26 percent of the anticipated cost of the projects.
The number of delayed projects decreases to 375 if the delay is calculated on the basis of the latest schedule of completion. Moreover, for 988 projects neither the year of commissioning nor the tentative gestation period has been reported.
Out of 525 delayed projects, 106 projects have an overall delay in the range of one to 12 months, 123 projects (13-24 months), 179 projects (25-60 months) and 117 projects (61 months and above).
The reasons for time overrun include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages.
Apart from this, delay in tie-up for project financing, delay in finalisation of detailed engineering, change in scope, delay in tendering, law and order problems, among others, are the other reasons. Also, state-wise lockdown due to COVID-19 is a reason for the delay in implementation of these projects.