Illustrative image – not actual.
As many as 425 infrastructure projects, entailing an investment of Rs 150 crore or more, have seen cost overruns of over Rs 4.83 lakh crore.
Of the 1,579 projects, 425 projects reported cost overruns and as many as 664 projects were delayed.
The total original cost of implementation of 1,579 projects was Rs 21,95,196.72 crore and their anticipated completion cost is likely to be Rs 26,78,365.62 crore, reflecting an overall cost overrun of Rs 4,83,168.90 crore.
The expenditure incurred on these projects stood at Rs 13,88,760.73 crore till March 2022, which is 51.85 percent of the anticipated cost of the projects.
However, the number of delayed projects decreased to 561, if delay is calculated on the basis of the latest schedule of completion.