Infra projects see cost overrun of Rs 1.72 lakh crIllustrative image – not actual.
As many as 331 infrastructure projects, each worth Rs 150 crore or above, have seen a cost overrun of Rs 1.72 lakh crore for various reasons including delays.

The total original cost of implementing 1,257 projects was Rs 15,76,903.56 crore, and their anticipated completion cost is likely to be Rs 17,49,274.62 crore, with a cost overrun of Rs 1,72,371.06 crore.

The projects incurred an expenditure Rs 6,80,016.96 crore till July 2017, which is 38.87 percent of the total anticipated cost. The 1,257 projects in question include 331 that have reported cost overrun, and 274 time escalation.

Out of a total of 1,257 projects, two projects have reported completion and 10 new projects have been initiated on the monitor of Ministry of Statistics and Programme Implementation. Of these, 11 projects are ahead of schedule, 304 are on schedule, and 274 are delayed. 331 projects are showing cost overrun and 92 projects are showing both, time and cost overrun with respect to original implementation schedules.

Also, for 668 projects, the original/anticipated commissioning dates were not reported by the authorities concerned.

Of the 274 delayed projects, 47 have overall delay in the range of 1-12 months; 59 have delay in the range of 13-24 months; 101 have delay in the range of 25-60 months; and 67 have delay of 61 months and above.

Of the 1,257 projects, 372 are mega projects worth Rs 1,000 crore and above. The total original cost of implementation of these projects was Rs 12,17,096.27 crore and their anticipated completion cost is likely to be Rs 13,60,528.92 crore.

The expenditure incurred on these mega projects till July was Rs 5,70,750.91 crore.

Out of the 372 mega projects, 130 have cost overruns with respect to original cost.