As many as 241 infrastructure projects including those delayed due to land acquisition, forest clearances and other reasons, have led to cost overrun of Rs 1.55 lakh crore.
The Statistics Ministry monitored 1,076 infrastructure projects, each worth Rs 150 crore or more across sectors such as power, railways and roads in March 2016.
It stated that 6 projects were ahead of schedule, 258 were on schedule, 343 got delayed, 241 reported cost overrun, and 83 projects reported both, time and cost overrun with respect to their original project implementation schedules.
As per the report, the expenditure incurred on these projects till March 2016 is Rs 5,75,677.42 crore, which is 41.31 percent of the anticipated cost of the projects.