Illustrative image – not actual.Union Railway Minister Piyush Goyal will inaugurate four-lane cable-stayed road overbridge (ROB) at Barddhaman in West Bengal on 30 September 2019. This is considered to be the country’s second largest ROB.
The work on the ROB has been completed in just 197 days or 6.4 months without affecting traffic for even a single day.
The cable-stayed overbridge is of 188.43 mtr high. Besides, 1.5 mtr wide footpaths on each of the sides parallel to the lanes, the overbridge has 27.7 mtr of width so as to accommodate vehicles on four lanes.
The project has been constructed at a cost of Rs 300 crore. The project has been completed under a 50:50 partnership between the Ministry of Railways and the West Bengal government.
The project envisaged re-building of existing ROB at Bardhaman over the Bardhaman-Durgapur railway line connecting Kalna Link Road and Katwa Road with G T Road.
The four-lane cable-stayed ROB encountered several issues in the process such as restriction of maximum height of the road surface clearances and also busy movement of rolling stocks over the yard. The challenges also included the construction of eight numbers of platforms, removal of impediments including 172 houses, 300 hard encroachments, 30 private buildings after land allocation, relocation of hospital, school, electric and water utilities.
The work on the ROB has been completed in just 197 days or 6.4 months without affecting traffic for even a single day.
The cable-stayed overbridge is of 188.43 mtr high. Besides, 1.5 mtr wide footpaths on each of the sides parallel to the lanes, the overbridge has 27.7 mtr of width so as to accommodate vehicles on four lanes.
The project has been constructed at a cost of Rs 300 crore. The project has been completed under a 50:50 partnership between the Ministry of Railways and the West Bengal government.
The project envisaged re-building of existing ROB at Bardhaman over the Bardhaman-Durgapur railway line connecting Kalna Link Road and Katwa Road with G T Road.
The four-lane cable-stayed ROB encountered several issues in the process such as restriction of maximum height of the road surface clearances and also busy movement of rolling stocks over the yard. The challenges also included the construction of eight numbers of platforms, removal of impediments including 172 houses, 300 hard encroachments, 30 private buildings after land allocation, relocation of hospital, school, electric and water utilities.