Illustrative image – not actual.The Indian Railways has reached out to the World Bank to terminate Rs 500 crore contract awarded to Beijing National Railway Group citing non-performance issues.
The contract pertains to signalling and telecommunication work in the Kanpur-Deen Dayal Upadhyay section of 471 km in the dedicated freight corridor which is funded by the World Bank.
The Dedicated Freight Corridor Corporation of India (DFCCIL) is implementing the freight corridor project. China Railway and Signal Communications Corporation, under the Beijing National Railway Research and Design Institute of Signal and Communication Group, bagged the project worth Rs 471 crore in 2016.
DFCCIL has reached out to the World Bank, which is funding the project, to cancel the said contract citing non-performance of the firm.
The progress in the project has been only 20 percent since the award, as per details shared by the Ministry of Railways.
If the World Bank does not agree upon it, the Indian Railways will terminate the contract by the end of June 2020 and the Central government funds to carry out the project.
Among reasons for termination of the contract, DFCCIL has cited non-availability of engineers, and authorised personnel at project site, stalled physical work with no local tie-ups, among other constraints.
This is the only project of DFCCIL which had been awarded to a Chinese company.
The contract pertains to signalling and telecommunication work in the Kanpur-Deen Dayal Upadhyay section of 471 km in the dedicated freight corridor which is funded by the World Bank.
The Dedicated Freight Corridor Corporation of India (DFCCIL) is implementing the freight corridor project. China Railway and Signal Communications Corporation, under the Beijing National Railway Research and Design Institute of Signal and Communication Group, bagged the project worth Rs 471 crore in 2016.
DFCCIL has reached out to the World Bank, which is funding the project, to cancel the said contract citing non-performance of the firm.
The progress in the project has been only 20 percent since the award, as per details shared by the Ministry of Railways.
If the World Bank does not agree upon it, the Indian Railways will terminate the contract by the end of June 2020 and the Central government funds to carry out the project.
Among reasons for termination of the contract, DFCCIL has cited non-availability of engineers, and authorised personnel at project site, stalled physical work with no local tie-ups, among other constraints.
This is the only project of DFCCIL which had been awarded to a Chinese company.