Illustrative image – not actual.
The Indian Railways is expecting to complete its electrification project on the Raninagar Jalpaiguri-New Bongaigaon-Guwahati section of the Northeast Frontier Railway (NFR) by December 2019.
The foundation stone for the project was laid by Railway Minister, Suresh Prabhu, on 10 November, 2016 at Maligaon.
The electrification project from Raninagar Jalpaiguri to New Bongaigaon and then from New Bongaigaon to Guwahati was assigned to Rail Vikash Nigam (RVNL), on a turnkey basis. The total cost of the project is Rs 655.55 crore.
Under the project, electrification of 382 km of the route and 687 km track of railway lines will be carried out.
The tender process for the project is expected to be completed within a short period. Electrification from Katihar to Raninagar Jalpaiguri is in an advanced stage.
The railway electrification project of 25 kV of Raninagar Jalpaiguri-New Bongaigaon-Guwahati section will also facilitate the launch of high speed trains and Main Line Electric Multiple Unit (MEMU) trains.
The electrification project will also involve upgradation of signalling systems at around 35 stations in the section for faster movement of trains.
The Raninagar Jalpaiguri-New Bongaigaon-Guwahati section will include building up of seven 220 and 132 kV traction substations and seven maintenance depots and sheds.