Illustrative image – not actual.It is located at 384/900 km-384/000 km on downline between Anangur-Caveri railway stations near Erode. The existing railway bridge, which falls under Salem Division, is of Brick Arch consisting of three spans of 9.15 mtr.
The existing railway bridge was proposed to be replaced with RCC segmental boxes comprising four spans of 6.6 mtr wide. Initially, the rehabilitation work was planned to be carried out with two temporary girders of 60 ft with crib support in the centre.
However, keeping in view the operation of less train services during the nationwide lockdown period due to the Coronavirus pandemic, the national transporter decided to rebuild directly without temporary girder for a continuous 36 hours block.
The rebuilding work was taken up on 4 May 2020 and completed on 5 May 2020. During this period, all the train services dealt on the single line between three stations -- Sankaridurg to Erode.