Indian Railways plans two new freight corridors by 2027Illustrative image – not actual.
After completion of Eastern and Western Deicated Freight Corridors (DFCs) by 2021. The Indian Railways will now take up the East-West DFC (EWDFC) and East-Coast DFC (ECDFC) which are expected to be completed by 2027. The two projects are expected to cost around Rs 1.23 trillion and may handle over 1,500 million tonne traffic by 2041-42.

The project completion cost was estimated based on the current price till 2026-27. The Dedicated Corridor Corporation of India (DFCCIL) also suggested a debt to equity ratio of 3:1 for the projects.

Based on the new plan, the EWDFC will be truncated and start from Sindi near Nagpur to Hijli near Kharagpur, covering 1,152.18 km and equated length (total length including connections with the Railways network) of 1,260 km. A total of 23 junction stations, three future junctions and 13 crossing stations have been proposed in this network which is expected to be completed at a cost of Rs 73,804 crore.

On the other hand, the ECDFC will start from Hijli to Kottavalasa near Vizianagaram in Andhra Pradesh. The total length in this corridor will be 750.91 km with an equated length of 830 km. This route will be having at least nine junction stations, one future junctions and 11 crossing stations. The expected investment for ECDFC will be around Rs 49,199 crore.

The EWDFC may handle around 449.88 million tonne traffic by 2031-32 and 690.6 million tonne by 2041-42. On the other hand, ECDFC may handle 405.11 million tonne by 2031-31 and 861.02 million tonne by 2041-41. By completion of the first two DFCs the total traffic of the Railways will increase by at least 144 million tonne by 2022.