In Phase-I of the Indian Railways’ Jayanagar-Bardiwas rail project, a speed trial was recently completed at a speed of 110 km per hour on 35 km long newly-gauge converted section between Jayanagar and Kurtha in Nepal.
The 68.72 km long Jaynagar-Bijalpura-Bardibas railway project has been entirely funded by the Indian government. According to the Railway Ministry, train operations on the Jayanagar-Kurtha section will facilitate movement between the two nations, as well as boost trade and develop surrounding regions.
The section from Jayanagar to Kurtha is 34.90 km and part of the Jaynagar-Bijalpura-Bardibas railway project of the Indian Railways.
The railway line from Jayanagar in the district of Madhubani, Bihar has been linked to Kurtha in Nepal under Phase-I of this project, earlier in 2021. The line was said to be extended up to Bijalpura by March 2021.
An amount of around Rs 550 crore has been spent by the government of India for the section up to Bijalpura which is further 17 km from Kurtha.
The new railway line, after Bijalpura, will be developed till Bardibas, once the land is handed over by the Nepal government for the project. Jayanagar is located four km from the India-Nepal border.
IRCON had undertaken the project and was reported that all rail engineering and infrastructure works were already complete.
To run trains on this railway route, KRCL had supplied two sets of 1600 HP DEMU passenger rakes. These DEMU rakes, which were handed over to Nepal on 18 September 2020, had two air-conditioned coaches each apart from non-AC coaches.