Chenab Bridge, the world's highest railway bridge, a part of the Udhampur-Srinagar-Baramulla Rail Link Project (USBRL), set an important construction milestone with completion of the steel arch of the bridge on 5 April 2021.
This was one of the most difficult parts of the bridge over Chenab. This achievement is a major leap towards the completion of the 111 km long winding stretch from Katra to Banihal by the Indian Railways.
The 5.6 mtr last piece of metal was fitted at the highest point and joined the two arms of the arch that currently stretch towards each other from both the banks of the river. This completed the shape of the arch that will then loom over the Chenab, flowing around 359 mtr below.
Post-completion of the arch work, removal of the stay cables, filling of the concrete in the arch rib, erection of the steel trestle, launching of the viaduct and track laying work will be taken up.
The Indian Railways is constructing the Arch Bridge on river Chenab as a part of the USBRL project to connect the Kashmir Valley to the rest of the nation. This is the highest Railway Bridge in the world being 359 mtr above the river bed level. The bridge is 1,315 mtr long. It will be 35 mtr higher than the iconic Eiffel Tower in Paris, France.
The Konkan Railway Corporation is the executing agency for the project by the Northern Railway. The Chenab Bridge Project Undertaking [Ultra-AFCONS-VSL (JV)] is contractor of the project. The cost of the bridge is Rs 1,486 crore.
The construction of the bridge involved fabrication of 28,660 tonne steel, 10 lakh cum earthwork, 66,000 cum concrete and 26 km motorable roads. The overall weight of the arch is 10,619 tonne. Moreover, the most sophisticated Tekla software has been used for structural detailing.
The process of arch closure started on 20 February 2021 and before the ceremony for closure of the arch, seven segments were erected in advance.
After the closure of the arch, the other activities such as removal of stay cables, filling of concrete arch with self-compacting concrete, erection of trestles, launching of deck over main arch by incremental launching will be undertaken.