The Northern Railway zone of the Indian Railways has completed electrification work of 130 km line in the states of Punjab and Haryana.
This will ensure that diesel locomotives are not used in the stretch anymore.
The railway lines that were electrified include Dhuri (Punjab)-Jakhal (Haryana) line which is 62 km long and Dhuri-Lehra Muhabbat single line in Ambala Division which is 68 km long. In these sections, a speed trial was done for up to 120 km per hour.
The section from Dhuri to Jakhal in Ludhiana-Dhuri-Jakhal railway line is a line connecting Ludhiana and Jakhal, while the section of Dhuri-Lehra Muhabbat falls in the Rajpura-Bhatinda railway line and will be significant as with electrification the mobility will improve.
While the major routes on the Northern Railway zone have been electrified, there are patches where trains get delayed because, on them, the electric locomotive has to be changed to diesel locomotive.
Now, with these sections being electrified, there will be a seamless travel with no delays.
The detailed safety inspections of Dhuri-Jakhal section and Dhuri-Lehra Muhabbat section was conducted using Motor Trolley. Additionally, on these sections, current collection tests as well as speed trials by electric locomotive were also conducted. The tests were done using Oliver-G technology.
During the inspection, several other structures such as RUBs, ROBs, FOBs, and level crossings on the line, stations as well as their amenities located on the sections were also reviewed.
As of now, electrification is done on over 40,000 RKM, which is 63 percent of broad gauge routes. A total of 18,605 km has been electrified during the period 2014-2020.
The Railways has set a target of electrifying 7000 RKM in FY21. Amid the COVID-19 pandemic, the Indian Railways has commissioned 365 RKM for electrification.
All railway routes on the broad gauge network are planned to be electrified by December 2023.