Illustrative image – not actual.Indian lenders -- banks and financial institutions -- to Dabhol Power Company (DPC) are scheduled to meet in Singapore on 22-23 April 2004, to take over the dollar-denominated debt and export credit guarantees.
It is reported that a special purpose vehicle, to be floated by existing lenders, would issue bonds that would carry government guarantee.
Indian lenders have an exposure of around Rs 6,200 crore to the 2,184 MW, twin-phase power project and five-million-tonne LNG terminal. The project has been lying idle since May 29, 2001. The 658-MW phase one is complete while only seven per cent of the 1,444-MW phase two remains incomplete.