Illustrative image – not actual.Indian
Aluminium Co Ltd (Indal) is planning to expand the capacity of its Hirakud
smelter in Orissa from the existing 30,000 tonnes per annum (tpa) to 60,000
tpa.
The
expansion would be carried out by transferring some 200 of the 400-odd unused pots
of the Belgaum smelter in Karnataka. It may be mentioned that full capacity
utilisation of the Belgaum smelter has not been possible due to power shortages
faced there. On the other hand, the Hirakud smelter is backed by its captive
power plant.
In
order to enhance capacity utilization at the Belgaum smelter, Indal plans to
enter into an agreement with the Karnataka State Electricity Board (KSEB)
whereby power would be wheeled in to the Belgaum smelter by Indal’s group
companies located in the region, through the KSEB.
If
this plan were to succeed, Indal may cease smelting operations at its 13,000
tonnes Alupuram plant in Kerala. The plant, in which case, would only focus on
downstream products.
Indal
has a total smelting capacity of 1.17 lakh tonnes per annum from three smelter
located at Belgaum (in Karnataka), Alupuram (Kerala) and Hirakud (Orissa). As
against this, aluminium production has been in the range of 42,000 to 45,000
tonnes.