Illustrative image – not actual.Indian Strategic Petroleum Reserves (ISPRL), will commission its strategic oil storage by January 2014.
The oil storage is being developed at Visakhapatnam in Andhra Pradesh, and Mangalore and Padur in Karnataka. The facilities will have a capacity to store about 5.33 million tonne of crude oil.
The Visakhapatnam unit will have a capacity to store 1.33 million tonne of crude oil in underground rock caverns. The underground cavities will be 10 storey tall and about 3.3 km long.
A similar facility in Mangalore will have a capacity of 1.55 million tonne and will be mechanically completed by March 2014. At Padur, near Mangalore, the storage facility will have 2.5 million tonne capacity and will be completed by the end of FY14.
The company has already completed 94.6 per cent work at Visakhapatnam storage, 89.2 per cent work at Mangalore, and 86 per cent work at Padur.
The Cabinet had in January 2006, approved building of the strategic crude oil storages at a cost of Rs 2,397 crore but due to cost and time overrun, the capital required is now estimated at Rs 3,958 crore.
The Visakhapatnam facility will cost Rs 1,038 crore; Mangalore Rs 1,227 crore; and Padur Rs 1,693 crore.
ISPRL has till date, received Rs 2,529 crore from the Oil Industry Development Board (OIDB), and Rs 100 crore from Hindustan Petroleum Corp. It requires Rs 1,195 crore either from OIDB or the government to complete the projects.