Illustrative image – not actual.India and Bhutan have entered into an MoU for preparing a detailed project report on Puna Tsangchu hydel power project in Bhutan. The project to come up on Puna Tsanghu River will have a capacity of 870 MW. Work on the project will commence on completion of Tala hydel power project.
As per the existing feasibility studies, a 141-metre high diversion dam will be located 10 kilometres downstream from the Puna Tsangchu bridge and an underground powerhouse, operating under a head of 310 metres, will be located 18 kilometres downstream from the bridge. The project will also have twin seven-kilometre long head-race tunnels conveying a total maximum discharge of 248 cumecs and 250 metre long twin tail-race tunnels. Feasibility investigations of the Puna Tsangchu project were taken up between 1998 and 2001 by the Electric Power Development Company (EDPC) of Japan through JICA.
The identification of the site was done in 1990-1992 by NORCONSULT-AS, a Norwegian consultancy firm. NORCONSULT-AS did the pre-feasibility study in 1992-1993 under the UNDP-NORAD project.
Addendum: WAPCOS has signed an agreement with the Ministry of External Affairs, Government of India, on 27 January 2004, for survey, investigation and preparation of DPR for the project.