Illustrative image – not actual.Indian Aluminium Company (Indal) is hopeful of achieving capacity expansion of its smelter at Hirakud in Orissa, by the end of September 2002, when it finishes shifting of idle equipment from its Belgaum smelter in Karnataka. Production may start in October 2002 and it would take another 4-5 months to the maximum capacity level.
The capacity of the Hirakud smelter is set to increase from 30,000 tonnes per annum to 57,000 tonnes per annum.
The company would invest around Rs.170 crore in transferring the first lot of pots. The company has started dismantling 200 electrolytic pots at its Belgaum smelter. The pots are used to melt alumina to produce aluminium metal. The Belgaum smelter has 400 pots. A decision to shift the remaining 200 pots would be taken at a later stage. The Belgaum smelter was closed in 1995 due to the high cost of power supplied by the state government. Indal does not own a power plant at Belgaum, but runs a 67.5 MW unit at Hirakud.