Illustrative image – not actual.Indian Aluminium Co, which is already in the midst of a capacity expansion, has planned a further 35-40 per cent hike in capacity.
The company has planned to raise the capacity of its Hirakud smelter to 1.35-1.40 lakh tpa from 1 lakh tpa. The feasibility report of this project is currently being prepared and a final decision on the project would be taken in the next two months.
Indal is currently hiking the Hirakud smelter capacity in Orissa from 65,000 tpa to 1 lakh tpa through the transfer of pots from its defunct Belgaum smelter in Karnataka. It is also enhancing power capacity at its captive power plant from 67.5 MW to 167.5 MW. The smelter expansion would be complete by October-November 2005 and another two months would be required till the plant reaches stability. The power plant expansion is expected to be completed by May 2005.