Ind-Barath shifts power project to TuticorinIllustrative image – not actual.

Hyderabad based Ind-Bharath Power Infra has decided to set up a 3x150 MW power plant at Tuticorin in Tamil Nadu instead of Hanakon in Karwar district of Karnataka. The company decided to shift the proposed plant to Tamil Nadu due to the lack of support from the locals and the delay in launching the project.

According to sources, the company was planning to set up the coal based power project at an outlay of Rs 1,800 crore. The land requirement is estimated at 220 acre and is likely to use a blend of imported and domestic coal, in a ratio of 80:20. The imported coal requirement is estimated to be 1.28 million tpa and will be sourced from Indonesian collieries.