Illustrative image – not actual.The increase in variation cost to the tune of Rs 650 crore has stalled the infrastructure works of Nadaprabhu Kempegowda layout for the past couple of months.
The Bangalore Development Authority (BDA) had engaged two companies – Larsen & Toubro (L&T) and SMPL Infra/Amrutha Constructions – for providing basic amenities in the 2,600 acre layout at a total cost of Rs 1,800 crore.
The layout comprises 23,000 sites with various dimensions. So far the contractors have been able to complete only 41 percent of the total work.
Among the works that were not factored in included construction of a substation. BDA decided to take up substation work for the electricity work only recently.
The work is expected to further delay the layout being put to use as the project needs another 18 months for its construction.
The Bangalore Development Authority (BDA) had engaged two companies – Larsen & Toubro (L&T) and SMPL Infra/Amrutha Constructions – for providing basic amenities in the 2,600 acre layout at a total cost of Rs 1,800 crore.
The layout comprises 23,000 sites with various dimensions. So far the contractors have been able to complete only 41 percent of the total work.
Among the works that were not factored in included construction of a substation. BDA decided to take up substation work for the electricity work only recently.
The work is expected to further delay the layout being put to use as the project needs another 18 months for its construction.