The agreement for development of two sections include 4-laning of Fagne-Gujarat/Maharashtra Border (Package-III) from 510 km to 650.79 km signed by Fagne Songadh Expressway and 4-laning of Amravati-Chikhli (Package-I) from 166 km to 360 km signed by Amravati Chikli Expressway.
The projects are estimated to cost Rs 1,885.74 crore and Rs 2,288.18, crore respectively. Both the projects are to be implemented on (BOT) toll basis with a concession period of 19 years including construction period of 910 days.