IL&FS Engineering and Construction Company has secured a Rs 162.58 crore Phulpur-Haldia Pipeline Project from GAIL.
IL&FS received a Fax of Acceptance (FOA) from GAIL for laying and construction of Section II pipeline from Chainage 159.70 km to receiving Terminal-cum-Future IP Station-4 at Dobhi Chainage 345.08 km in Bihar.
The 30 inch pipeline with a total length of 185.38 km will be mechanically completed in a span of 15 months from the date of FOA. In addition, the company will require three months more for drying, commissioning and GAS-IN.