IL&FS receives Rs 1,925 cr for Gurugram MetroIllustrative image – not actual.
Infrastructure Leasing & Financial Services (IL&FS) has received Rs 1,925 crore from the Haryana Shehari Vikas Pradhikaran (HSVP) as interim termination payment for the Gurugram Rapid Metro System that is now run by the Delhi Metro Rail Corporation (DMRC).

The Supreme Court had, on 26 March 2021, directed HSVP to deposit 80 percent of the total debt due amounting to Rs 2,407 crore within three months into the escrow accounts of the two IL&FS subsidiaries, Rapid Metro Rail Gurgaon (RMGL) and Rapid Metro Rail Gurgaon South (RMGSL).

The use of money that has flowed in the escrow accounts will be subject to the orders of the NCLAT or any other competent legal authority under the Supreme Court ruling.

The resolution of Rs 1,925 crore forms part of the resolution of Rs 61,000 crore total recovery estimated by the government-appointed IL&FS board. This represents resolution of over 61 percent of overall debt of about Rs 99,000 crore (fund based and non-fund based) as of October 2018.

Two other SPVs of IL&FS subsidiary IL&FS Transportation Networks (ITNL) are also seeking resolution of disputes with the Jharkhand government for Rs 500 crore payment in annuities. A case was filed in the Jharkhand High Court in March 2021.

The Jharkhand SPVs were involved with construction of Ranchi Ring Road Section of VII on build, operate and transfer basis and a 23 km road patch on NH-33. The projects were developed with semi-annual annuities of around Rs 225 crore.

Andhra Bank is the lead bank in the RMGL along with Punjab National Bank, Indian Overseas Bank, Indian Bank, Punjab & Sindh Bank, UCO Bank, Bank of India and Dena Bank (presently Bank of Baroda). Canara Bank is the lead bank in RMGSL along with Andhra Bank, Corporation Bank (presently Union Bank of India), Punjab & Sindh Bank, Central Bank of India and IIFC (UK).

IL&FS had bagged the two-phased Gurugram Metro Project developed through RMGL and RMGSL in 2009 and 2013 but RMGL and RMGSL terminated the concession agreements in September 2019 due to disputes that had impacted the commercial operations of the systems.

These SPVs demanded termination payments under the concession agreement. HSVP had, however, refuted the contention of RMGL and RMGSL citing concessionaire event of default and challenged the matter in High Court of Punjab and Haryana.

The High Court ruled in September 2019 that O&M of the Metro Link be handed over to HSVP and directed CAG to carry out financial audit of total debt due; and thereafter HSVP to pay 80 percent of due debt determined by CAG in the escrow account within 30 days of submission of CAG report; and sought that all other disputes be settled through arbitration.