Illustrative image – not actual.Infrastructure Development Finance Company (IDFC) will lead-arrange Rs.500 crore reforms-based debt for Karnataka Power Corporation (KPCL), which is executing the 210 MW coal-based Raichur power project in Karnataka. IDFC has reportedly postponed the deadline for achieving the preset milestones for power sector reforms.
It may be recalled that debt for the
Rs.646 crore project is linked to the State’s power sector reforms. The pre-conditions
include,
·
Dividing the State into distribution circles covering
different regions by December 2000,
·
Finalisation of the structure of the State’s
electricity sector by March 2001,
·
Segregation of assets and operationalisation of distribution
companies by June 2001,
·
Privatisation of the Karnataka Power Transmission Corporation
(KPTCL) by December 2001,
·
Implementation of the tariff orders passed by the Karnataka
Electricity Regulatory Commission (KERC).
The
State Government had defaulted on its first commitment of dividing KPTCL’s
distribution network into different regions. Also, the Government has implemented
the KERC’s tariff orders only partially.