Illustrative image – not actual.The Infrastructure Development
Finance Corporation (IDFC) has laid down the following conditions for
sanctioning a Rs.100 crore loan for the 210 MW Raichur (7th unit) thermal
power project.
- The State’s power sector to be privatised. Presently,
Karnataka Power Corporation (KPCL) is in charge of power generation, while
the Karnataka Power Transmission Corporation (KPTCL) is in charge of
transmission and distribution (T&D). The privatisation is to be
carried out on the advice of a consultant, who will also draw up a
financial restructuring plan for KPTCL.
- The proceeds from the privatisation be deposited
in a dedicated power sector fund, to be utilised by the State government to
meet its obligations in the power sector.
- The State government should make public the demand-supply
situation in the State’s power sector. This is to make lenders and investors
aware of the risks involved in power sector funding.
- The State government, KPCL, KPTCL should agree
to comply with all the orders of the Karnataka Electricity Regulatory Commission.
- Transactions between the State government, KPCL
and KPTCL should be on a commercial basis.
- An energy audit to determine T&D losses to
be completed by March 2001 and metres to be installed for all consumers by
June 2003.
- Dues of the State’s power utilities to be
securitised and bonds issued.