Illustrative image – not actual.Industrial Development Bank of India (IDBI) has reduced the loan sanctioned to the 455 MW Gautami power project, from Rs.409 crore to Rs.350 crore.
The Rs.409 crore sanctioned by IDBI
earlier was for two separate projects, NCC Constructions (239 MW) and Gautami Power
(359 MW), which were merged to form a single power project of 455 MW. The
revised cost of the merged project is estimated at Rs.1,325 crore.
The change in the size and cost of
the project follows the Andhra Pradesh government discouraging the use of
naphtha and promoting the use of liquefied natural gas. In 1999, when IDBI had
sanctioned loans for the two projects, both were naphtha-based. As the allocation
of gas by the State was not adequate to meet the combined 598 MW capacity, it
was decided to merge both projects and reduce the size to 455 MW. The gas would
be allocated by Gas Authority of India.
IDBI would sanction the foreign currency
portion of the loan to the extent of Rs.350 crore for the import of necessary
equipment. Of the total project cost of Rs.1,325 crore, Rs.400 crore is by way
of equity and the balance is through term loans.