Illustrative image – not actual.ICICI has agreed to pick up a 28 per cent equity in the 300 MW Baspa hydel project in Himachal Pradesh. The project, which is being implemented by Jaiprakash Hydro Power Ltd (JHPL) is estimated to cost Rs.1,620 crore.
The project has an equity component of Rs.485 crore. While
Jaiprakash Industries (JIL), the promoter of JHPL, will be bringing in Rs.350
crore as equity, the remaining Rs.135 crore will be brought in by ICICI. In
fact, JIL and ICICI have already contributed Rs.220 crore and Rs.75 crore,
respectively, towards their equity.
The debt component of Rs.1,135 crore, comprises sanctioned
rupee term loans of Rs.425 crore and non-convertible debentures worth Rs.300
crore. A foreign currency loan of Rs.230 crore has also been sanctioned,
leaving only Rs.180 crore worth of term loans, which have yet to be sanctioned.
The project, which was scheduled for completion by
July 2002, has been delayed due to the unprecedented floods in the Sutlej river
in July 2000. The floods caused damaged approach roads and washed away bridges
at Karcham and Tapri. This completely stopped the project work, which was
resumed only in April 2001.
The project is now expected to be completed by 31 July
2003.