Illustrative image – not actual.Integral Coach Factory is implementing an expansion plan to manufacture 101 rakes (of nine coaches) of dual voltage EMUs (electric multiple units) for Mumbai Rail Vikas Corporation.
ICF will undertake an expansion project, including new machinery and additional infrastructure, in the factory at a cost of Rs.47 crore.
The foundation stone for the construction of new shed on Line VIII of main assembly shop in ICF's furnishing division was laid. The estimated project cost is Rs.2.48 crore and work is likely to be completed by December 2005.
Foundation stone was also laid for provision of 10 tonne gantry crane in Bays III and IV of partition frame assembly in shell division. The project cost is Rs.1.23 crore and expected to be completed by February 2006.
Besides this, foundation stone was also laid to expand Bays III, IV and V in sidewall assembly shop of shell division. This project is estimated to be around Rs.70 lakh and is likely to be completed by January 2006.