Hyderabad metro rail project cost revised to Rs.11,814 croreIllustrative image – not actual.

The government has once again revised the Hyderabad metro rail project cost from the Rs.9,696 crore to Rs.11,814 crore due to the increasing traffic density in the city. The project cost has been revised for the fourth time by the Union government. Meanwhile, the HMR has postponed opening of financial bids due to revision of project cost.

When the detailed project reports were prepared by the Delhi Metro Rail Corporation in 2003, the project cost was Rs 6,746 for two corridors - Chaitanyapuri to Miyapur and Secunderabad to Falaknuma. Later, it was decided to add another corridor from Habsiguda to Hi-Tec City. The project cost was revised to Rs.8,482 crore and the corridors were extended to 77 km from 67 km. The metro corridor was extended up to Nagole from Habsiguda and Shilparmam from Hi-Tec City. As a result of this, the cost has increased to Rs.9,696 crore.

It is learnt that, the Hyderabad metro rail (HMR) officials had proposed 219 coaches for metro trains on all three routes - LB Nagar to Miyapur, JBS to Falaknuma and Nagole to Shilparamam - based on traffic projections for 2008. Since the traffic flow scene has changed drastically in the last five years, the Centre has decided to take traffic projections till 2013, by when the metro rail project is expected to be completed, and increase the number of coaches in the trains.

Though traffic experts have recommended 372 coaches for all the three corridors, the central government has sanctioned 327 coaches.

← All latest storiesBack to top →