Hyderabad Metro Rail project attains 75 percent overall progressIllustrative image – not actual.

The 72 km long elevated Hyderabad Metro Rail (HMR) project, presently under construction, has attained 75 percent overall progress.

Several properties required for the development of the project have been acquired. A total amount of Rs 2,902 crore towards the project was spent in 2016, of which L&TMRH spent Rs 2,742 crore and HMR spent Rs 160 crore.

The cumulative expenditure towards the project is Rs 14,172 crore, so far. It has attained 75 percent overall progress as the company has completed 2,340 foundations in 61 km, viaduct in 50 km, 2,231 pillars in 58 km, and a major portion of work in signalling, overhead electrical traction and telecommunication systems, and at stations.

L&T Metro Rail Hyderabad (L&TMRH) is constructing the 72 km elevated HMR project which will have three corridors and 66 stations.

All the 57 three-car trains from Hyundai Rotem, South Korea, have been obtained, and sanction of the commissioner for Metro Rail Safety (CMRS) for the Miyapur SR Nagar section of 12 km of corridor-I was also received.

The metro project was initially scheduled to be completed by July 2017. However, due to delays such as land acquisition, changes in alignment etc, the deadline of the project will be postponed.

 