Hyderabad airport project: Site preparation work completeIllustrative image – not actual.

Hyderabad International Airport Ltd has announced the complete of site preparation works of the upcoming Hyderabad international project in Andhra Pradesh.

The foundation stone for the Rs.1,760 crore project was laid at the hands of Ms Sonia Gandhi, Chairperson, National Advisory Council (UPA government) on 16 March 2005.

Further, around 15 per cent of the work relating to the passenger terminal building, including the air traffic control tower, has been completed.

HIAL, a joint venture company promoted by GMR Group and Malaysia Airports Holding Berhad to implement the project, achieved financial closure in August 2005. While L&T had won the contract for airside and landside works, China State Construction and Engineering (HK) got the passenger terminal building works.

During 2006, the shell of the passenger terminal building, ATC tower and major portion of runway works would be completed. Besides, finalisation of cargo contracts, maintenance and repair overhaul, fuel farm and other retail concessionaires is scheduled to take place in 2006. 

The project is likely to be completed by November 2007. Considering a three-month period for statutory tests and permissions, the airport is likely to be operational by March 2008.

Phase I of the airport would handle seven million passengers and more than one lakh tonnes of cargo. The ultimate capacity of the airport is over 50 million passengers.