Hutti Gold Mines Company (HGML) has chalked out Rs 352.11-crore expansion plan to be implemented over the next five years.

The expansion plan includes extraction of gold below 2,000 ft at Hutti in Raichur district of Karnataka and installation of a new shaft with six-mtrs radius. The company has a cash reserve of Rs 361 crore.

HGML has roped in Ranchi based Central Mine Planning and Design Institute for preparation of a mine plan for Phase II mining at Hutti and tender documents for floating a global tender for the supply and installation of new shaft. Setting up of the new shaft is estimated to cost Rs 204 crore. The shaft is likely to be installed from the surface up to 1,000 mtrs below the earth and the installation is to be completed in four years. Post installation of the new shaft, HGML will be able to take up gold mining from 2,000 to 2,800 ft below the earth.

Further, the company is likely to invest Rs 68.22 crore in its new snag ball mill at Hutti which is scheduled to be completed by end-January 2010. The existing capacity of the ore milling unit at Hutti is to be expanded to 2,000 tpd when the ongoing work on the new snag ball mill will be completed. So far, 90 per cent of the building works on the plant and the assembling of the milling plant has been completed.

While the company plans to reopen the defunct Gray Shaft at the south end of the mining area at an investment of Rs 16.32 crore, it is likely to computerise the existing mechanical system for controlling the whole operation of mining and milling units at an estimated cost of Rs 2.77 crore.

This apart, the company is planning to take up underground mining activity at the Ooty and Hirabuddinni areas once the open cast mining comes to an end. It is likely to invest Rs 14.85 crore in Ooti Gold Unit (open pit mine) development, Rs 25 crore on ore milling unit.

Besides, HGML is planning to form JVs with NMDC, Australia based firm Cluff Resources Pacific NL, and Deccan Gold Mines to begin mining in Davanagere, Tumkur, Gulbarga, Chitradurga, Shimoga and Dharwad in Karnataka where gold minerals are found. It has set aside Rs 12.09 crore to take up gold mining in Chitradurga, Davanagere and Shimoga districts where the preliminary survey work has been completed.

The company has sought the Karnataka Government's approval for the proposed JVs.