Illustrative image – not actual.Housing and Urban Development Corporation (Hudco) has sanctioned a Rs.140 crore loan assistance for the upgradation of two thermal power plants in Uttar Pradesh. The Uttar Pradesh government provided the free guarantee against the Hudco loan on 01 January 2009.
The funds will be used for installing electro-static precipitators (ESP) in three units at Harduaganj and in two units at Parichha power plants in Aligarh and Jhansi districts which are owned by UP Vidyut Utpadan Nigam. The State Pollution Control Board had provided a NOC for the expansion programmes of these power plants on the condition that ESPs will be installed soon.
The total project cost is Rs.180 crore, of which 70 per cent will come from debt and 30 per cent from equity to be provided by Hudco and the state government, respectively. UP Vidyut Utpadan Nigam has already placed the order for ESP with Bharat Heavy Electricals.
The two plants have an installed capacity of about 700 MW. The whole project is likely to be completed by the 2009-10.