HUDA's outer ring road project delayedIllustrative image – not actual.

 The second phase of Outer Ring Road (ORR) project is likely to get delayed as the Hyderabad Urban Development Authority (HUDA) is facing hurdles in acquiring land for the project.

The Phase-IIA work, which was supposed to begin from 15 August 2007, is now likely to begin by October 2007. The 62 km Phase-IIA of ORR will extend from Narsingi to Patancheru, and from Shamshabad to Pedda Amberpet.

Of the total 2,050 acres of land required for the project from Narsingi to Patancheru and Shamshabad to Pedda Amberpet, HUDA could acquire only 1,350 acres.

The Phase-IIA of the project has been divided into five packages and contracts were finalised in May 2007. As per the agreement, 50 per cent land has to be handed over to the contractors when the work begins. The acquisition got delayed due to the procedures as per Land Acquisition Act.

The ORR Phase-II is being taken up from Shamshabad to Patancheru, and it is divided into A and B. Accordingly, Phase-IIA (about 62 km) is from Shamshabad to Pedda Amberpet while the 75-km-long phase-IIB extends from Peddamberpet to Patancheru. Phase-II A is again divided into two stretches - Shamshabad to Peddamberpet and Narsingi to Patancheru.

It is estimated that the Phase-IIA will cost Rs.1,731 crore while the Phase-IIB project will cost Rs.2,090 crore. The Phase-IIA between Narsingi and Patancheru is being taken up on 'annuity model' where the contractors of five packages will form into a special purpose vehicle (SPV) with the Hyderabad Growth Corridor (HGCL), which was created for taking up ORR. After the formation of SPV, HUDA will give a letter of acceptance to contractors.