Himachal Pradesh Power Corporation (HPPCL) has commissioned the first unit of 50 MW of the 100 MW Sainj Hydro Power project.
The project has been commissioned and synchronised with the northern grid through Parvati-Kol Dam transmission line.
The impounding of water in the reservoir commenced on 2 February, 2017 and mechanical testing was done successfully on 25April, 2017.
The second unit of 50 MW will also be commissioned soon. The project will produce 322 million units of electricity per year accruing an income of Rs 100 crore to the state government.
The company will provide 100 units of power per month to the families affected by the project, for a period of ten years. In addition, affected families will also get one percent of income from the project, while 1.5 percent of income will be contributed to Local Area Development Authority (LADA).