HPL Additives plans to set up an Azodicarbonamide manufacturing unit with a capacity of 7,200 tpa at Derabassi in Patiala district of Punjab.

In November 2018, HPL Additives received environment clearance (EC) for the project and work was likely to commence by March 2019.

As per information collated by Projects Today, the project is delayed as the company was awaiting approvals from the Central and state government.

Work on the project was expected to commence by April 2020 with completion scheduled for April 2021.