HPCL's pipeline to be ready by March 2002Illustrative image – not actual.

Hindustan Petroleum Corporation Ltd's (HPCL) Vijayawada-Hyderabad pipeline will be completed by March 2002. According to Mr N.K.Puri, Chief General Manager, about 78 per cent of the pipeline work has been completed.

 

The Rs.185 crore pipeline can be used to transport petrol, diesel, kerosene and naphtha. It will measure 223 kms in length and will have a capacity of 5.5 million tonnes per annum.

 

The pipeline is part of HPCL’s Vizag-Secunderabad pipeline, which is estimated to cost Rs.345 crore.