HPCL's Bhatinda refinery: Financial closure by end-2005Illustrative image – not actual.

Hindustan Petroleum Corporation has targeted to achieve financial closure for its 9 million tpa greenfield petroleum refinery project in Punjab, by December 2005.

HPCL expects to tie up Rs.6,000 crore as domestic debt, for which negotiations are in an advanced state. The foreign debt component will be linked to the order of equipment. The project cost (1998 prices) is Rs.9,806 crore and would be financed through a debt-equity ratio of 3:2.

The petroleum refinery project, which would be implemented through a special purpose vehicle callled Guru Gobind Singh Refineries Ltd, will also have a Rs.2,500-crore crude pipeline from Mundra in Gujarat to Bhatinda in Punjab. The total project cost would thus work out to over Rs.12,500 crore.

The refinery would produce Euro IV grade fuel and a range of petrochemical products using the fluid catalytic (FCC) route.

HPCL is keen on implementing the project as a 50:50 joint venture with a foreign partner that has yet to be identified. HPCL has planned to even float an IPO to dilute its holding after the project is commissioned. In the final scheme of things, HPCL and its foreign partner would have a stake of 26 per cent each, while 48 per cent would be widely-held.