Illustrative image – not actual.HPCL intends to augment capacity at its oil refinery in Visakhapatnam in Andhra Pradesh.
The company has chalked out a capex plan of Rs 13,000 crore for raising its capacity to 15 million tpa by 2014. land acquisition has already been completed and the detailed feasibility report (DFR) for expansion is to be ready soon.
HPCL is likely to add a new 1,80,000 bpd crude distillation unit (CDU) and scrap the old 36,000 bpd unit at the refinery. Currently, it operates three CDUs at 1,66,000 bpd at the refinery.
Meanwhile, HPCL is also looking at investing Rs 30,000 crore to set up an 18 million tpa refinery in Maharashtra. The land earmarked for the refinery is located between Ratnagiri and Raigad and the unit - Maharashtra Refinery - slated to be completed within 48 months from the date of receipt of all approvals.
HPCL and Mittal Energy's nine million tpa refinery at Bathinda, in Punjab is likely to be mechanically complete by March, 2011, and the unit will be fully operational by September 2011.