HPCL faces hurdles in Rajasthan refinery project Illustrative image – not actual.

Hindustan Petroleum Corporation (HPCL), is facing huge water requirement issues in its refinery project at Pachpadra in Barmer district of Rajasthan.


The project, with nine million tonne capacity, is estimated to cost Rs 37,320 crore. It will require 127 million ltr per day of fresh water. However, the Rajasthan government has assured supply of five to six million gallon of water a day for the refinery project from the Indira Gandhi canal. It has also agreed to give an interest-free loan of Rs 3,736 crore per annum for 15 years to the unit after commercial production starts.


The refinery, which is planned to go on-stream in four years, will source half its crude oil from Cairn's Barmer oilfields, while the remainder will be imported. The Rajasthan government will have a 26 per cent stake in the project.

 