Siri Ram Syal & Son Construction of New Delhi has been selected as the implementing agency of the 4.5 MW (2x2.25 MW) Bakhli hydel power project in Mandi district of Himachal Pradesh.

 

The project, costing Rs.28.80 crore, envisages the installation of 2 units of 2.25 MW each on Bakhli Khad, a tributary of River Beas.

 

The broad features of the project are:

 

  1. Trench type diversion weir.
  2. Rectangular type desilting tank if size 45m x 9m x 4.1m of varying depths to exclude silt particles of size 0.3mm and above.
  3. 49.25 metres long water conductor system.
  4. A rectangular forebay of size 45m x 6m x 3.5m
  5. A surface type powerhouse of size 30m x 12m x 9m.
  6. A 33 KV outdoor switchyard near the powerhouse.                  

 

 

 