Illustrative image – not actual.The Hosur Ring Road project is nearing completion and it will decongest the traffic from Bengaluru to Tamil Nadu via Hosur town.
The two-phased project, for a total length of 8.85 km, was taken up by the State Highways Department. It is being implemented under the National Service Scheme and is being completed at a cumulative cost of Rs 16.43 crore.
Phase-I work, spanning over a length of 4.85 km, was completed in 2011 at a cost Rs six crore, while Phase-II is being completed at an expense of Rs 10.43 crore. The remaining section is nearing completion in Phase-II.
The remaining work includes median greenery, board markers, reflectors and other ancillary safety measures.
With the Highways Department moving on to the globally-tested Performance Based Maintenance Contract (PBMC) model, any further BT works will be awarded only after the road is left running for five years.